Ras AL Khor Crossing (RAKC)

Consultant: Parsons overseas
Contractor: W J amp; P LLC
Waterproofing Contractor: BMC Gulf LLC

Environmental

Abu Dhabi Golf Course

Lake Line System.

Environmental

Abu Dhabi Storm Water Manholes

A project that required a high level of professionalism and a sense for detailing. Difficult working conditions and limited access in some confined areas, required a good discipline and a willingness from our technical staff to manage and execute this project. The CPL lined manhole can be welded on the internal HDPE lining of the 2m diameter pipes creating a strong connection and minimizing the risk of leakages at this usually weak point in any pipe to manhole connection.

Environmental

Bridge Water Proofing

This project is considered to be the pioneer project for RADCON #7 in the UAE. The material was approved as an alternative to the specified Polyurethane membrane. It advantages of using Radcon #7 in this application were mainly the fast and simple application of the product. The immediate traffic-ability of the areas once the product was absorbed by the concrete and the 100% watertight status achieve after only 3 days of product application.

Environmental

Commercial Villas

The execution period was two months to complete 2,200 sq.m of stamped concrete flooring which is an alternative pavement to natural stone, slate, brick and other expensive materials. The procedure is treating the surface of freshly poured concrete – on job site – with factory prepared ready to use powders and stamping it with rubber mats.

Environmental

Dam Construction

Lining System for the main dam concrete and three breakers (Gabion)

Environmental

Dubai Festival City

Lining of lakes, streams / waterfalls in a new 18 holes Golf Course. Construction work also included special detailing for tunnels / culverts existing on site, which had to be sealed and protected from the surrounding waters. The Golf Course design was made by one of the best Golf Course designers internationally.

Environmental

Dubai Media City

Lake Lining System for Atrificial Lakes

Environmental

Emirates Hills

The execution period was very tight to complete over 700,000 sq m of liner. We had to work over 16 hours a day to finish the job on schedule.

Environmental

Foundation Water Proofing

As a matter of fact, more than 60% of the buildings in Abu Dhabi city are facing problems with underground water infiltration into their basements. This is due to the usage of conventional waterproofing systems, not capable of withstanding the high underground water pressure. This project was a challenge for us and our materials. With a connection providing a pullout strength of over 41 tons per m², the CPL system provides a strong mechanical bond between the concrete and the membrane, not allowing any water to track between them.

Environmental

Grand Hayat Water Proofing

Beautiful landscaped streams, waterfalls and a jungle like experience in the main atrium area with trees, plants / bridges. This project was a challenging experience due to the complicated setup, narrow shaping and critical requirement for waterproofing capabilities due to the internal use of the liner within the Hotel lobby.

Environmental

Hafira Landfill

The execution period was two month to complete 135,000 sq m of GSE HDPE Liner during winter time.

Environmental

Irrigation Water Tanks

This project consists of 5 Water Tanks belonging to Agricultural Department in Abu Dhabi Municipality. Tanks are designed to contain 2 million Gallons each and used for water irrigation of 800 Farms.

Environmental

Jebel Ali Landfill

The landfill features a large size excavation with a total depth of 12 meters and very steep slopes.

Environmental

Jizan Shrimp Farm

This quality project has been put in operation in January 2003, the project is located in a city called Jizan in the southern part of Saudi and adjacent to the Yemeni borders, it falls on the Red sea. The project is expected to have an annual average exports of 400 tons of high quality shrimp.

Environmental

Jumeirah Islands

Jumeirah Islands project is a planned urban development shaped and designed on 300 hectares of land, located just off Sheikh Zayed Road between Interchange 5 and 6. With strict focus and commitment to create a natural environment on Jumeirah Islands, water for the canals / lakes is being underground flushed from the Arabian Gulf, where BMC Gulf installed 950,000 sqm of HDPE liner to provide water tightness for these canals and lakes, numerous water falls and water designs are strategically placed on the project for continuous flow where BMC introduced special lining systems.

Environmental

Khalifa Park

Stamped concrete applied to 8,000 m2 of a public park.

Environmental

Meadows and Springs

The project involves lining of 37 artificial lakes. The areas of the lakes are ranged between 2000 sq m and 115000 sq m. The total area of the lakes is 700,000 sq m. The lining works started in this project started in July 2003 and is expected to be completed by the end of July 2004.Quantity: 700,000 sq m Liner.

Environmental

Millennium Hotel

Vibration and noise control.

Environmental

Raslaffan Landfill

The landfill is located within the Raslaffan facility a high security level area, which demanded good organization and discipline from our site engineers and technicians during the execution of the job. All stages of the project were carefully monitored and controlled by the consultant in order to assure an installation done to their satisfaction. BMC has been awarded with an appreciation certificate for the project management and installation quality.

Environmental